Year |
|
Client, Project and Location |
|
Responsibilities |
2013 |
|
MOGAS Industries, Houston, TX |
|
1-year rep contract. |
2013 |
|
North West Redwater Partnership, Canada |
|
Identify critical valves to ensure best fit for application and assist in creation of plant-wide database of all valves. 1-year contract. |
2013 |
|
Denbury Resources, Plano, TX |
|
Produce valve audits and develop data base for 2200 valves for purchasing and material certification verification. 2-year contract. |
2013 |
|
Eii Valve, Houston, TX |
|
Design services to develop new trunion product line and double block and bleed valve to include: product review and approval for drawing, BOM and material selection; product prototype review and approval for assembly, testing and validation. 1-year contract. |
2012 |
|
LukOil/Burgas, Bulgaria |
|
Lead consultant for valve selection for €900M H-oil unit project. Technip (Rome) EPC. |
2012 |
|
GOG consusultants |
|
|
2012 |
|
McIlvane Company, Illinois, USA |
|
Provided consulting studies to market research firm on surge control valve compressor and gasket and packing valve |
2011 |
|
MOGAS Industries, Houston, TX |
|
Project manager responsible for review of all Total (France) Fire Test documentation before submittal. |
2011 |
|
Cornerstone Valve, Houston, TX |
|
Created product business plan market report for (new product for) power and (existing product line for) refining |
2010 |
|
LukOil/Axens T-Star Unit Perm, Russia |
|
Engineer responsible for review, walkdown, and changeout of catalyst loading/unloading and catalyst regeneration systems. P&ID, HAZOP and operational discussions and reviews. |
2009 |
|
LukOil/Axens T-Star Unit Perm, Russia |
|
Engineer responsible for review, walkdown, and changeout of catalyst loading/unloading and catalyst regeneration systems. P&ID, HAZOP and operational discussions and reviews. |
2007/8 |
|
GS Caltex/GS Engineering/CLG LC-Finer Unit Yeosu, South Korea |
|
Engineer responsible for specification of all severe service isolation valves for this unit. Purging, coatings, material, and controls recommendations. |
2006 |
|
Shenhau/SEI/Axens Coal Liquefaction Unit |
|
Engineer responsible for specification of all severe service isolation valves for this unit. Purging, coatings, material, and controls recommendations. |
2005 |
|
Neste/Jacobs/CLG LC Finer Unit Porvoo, Finland |
|
Engineer responsible for specification of all severe service control valves for this unit |
2004 |
|
Gas Oil Hydrotreating Unit Haifa, Israel |
|
Engineer responsible for specification of all severe service control valves for this unit |
2003 |
|
BPCL/EIL Chevron Isocracker Unit Mumbia, India |
|
Engineer responsible for specification of all severe service control valves for this unit |
2002 |
|
Premcor (Valero Presently) / FW Delayed Coker and Chevron Isocracker Units Port Arthur, Texas |
|
Engineer responsible for specification of all control valves for these units |
2001 |
|
BASF Ethylene Plant Port Arthur, Texas |
|
Engineer responsible for specification of all control valves for this plant |
2000 |
|
ExxonMobil/COP Delayed Coking Unit Baytown, Texas |
|
Engineer responsible for specification of all control valves for this unit |
1997 |
|
Snamprogetti/PKN Orlen Grassroots Axens H-Oil Unit in Plock, Poland |
|
Engineer responsible for specification of all control valves for this unit. Scope included valves around feed, reactor, catalyst and distillation sections of unit. |
1996 |
|
Formosa Supercritical Power plant (5-units) |
|
Engineer responsible for selection and design of high pressure Turbine bypass system (#4500 ANSI class system). |
1995 |
|
Snamprogetti/Pemex Grassroots Axens H-Oil Unit in Tula Refinery |
|
Engineer responsible for specification of all control valves for this unit. Scope included valves around feed, reactor, catalyst and distillation sections of unit. |
1995 |
|
Fluor Daniel/SK Energy Grassroots Chevron Isocracker Unit in Ulsan Refinery |
|
Engineer responsible for specification of all control valves for this unit. Scope included specification of severe service valves around feed, reactor, separator and distillation sections of unit. |
1995 |
|
ExxonMobil/Tonen Grassroots Axens H-Oil Unit in Kawasaki Refinery |
|
Engineer responsible for specification of all control valves for this unit. Scope included valves around feed, reactor, catalyst and distillation sections of unit. |
1994 |
|
Formosa Ethylene Expansion in Taiwan |
|
Resident engineer working with two other engineers to specify over 600 control valves for this project |
1994 |
|
Public Service of Oklahoma Tulsa Plant Re-Power Project |
|
Field engineer responsible for plant walk down and assessment of all critical service valves for unit re-start |
1993 |
|
FW/KNPC Restart of 3 Major Refineries in Kuwait after Gulf War |
|
Field engineer in charge of coordinating the repair of over 3000 control valves and troubleshooting and training of refinery personnel |
1993 |
|
KBR/CF Industries Grassroots Stamicarbon Urea Plant, Donaldsonville, Louisiana |
|
Resident engineer responsible for specification of all high pressure manual and control valves. Special 25-22-2 high nickel steel used for corrosion purposes with special NDE requirements. |
1992 |
|
KBR/Pertamina Grassroots Ammonia Plant Indonesia |
|
Resident engineer responsible for specification of all standard and severe service control valves. Over 200 valves specified on this project. |
1992 |
|
KBR/ExxonMobil Beaumont Refinery Expansion Beaumont, Texas |
|
Resident engineer responsible for over 500 control valves specified in 11 different operating units.
|
1991 |
|
Stone & Webster (Shaw) Crude Stabilization Plant in Hatew Field |
|
Resident engineer responsible for the specification of all control valves and severe service valves for plant. Duplex stainless steels with NACE certification were applied on this plant. |
1990 |
|
Coastal (Valero) Aruba Refinery Revamp / Debottleneck Aruba, Antilles |
|
Control system engineer responsible for evaluation of existing control systems assessment and replacement to allow for crude distillation units to be restarted |
1989 |
|
ExxonMobil Olefins Plant Expansion & Debottleneck Baytown, Texas |
|
Control systems lead engineer on grassroots propylene recovery unit responsible for specification of all valves and field instrumentation for unit |
1988 |
|
BASF Debottleneck Freeport, Texas |
|
Control systems engineer responsible for instrumentation and valve specifications for hydroxalimine unit revamp and expansion |